I would like display resource names on top of Gant Chart bars.
Is there any way to do this?

I have 20 sub projects each with uniue WBS number.

Gantt chart bars show start date and end date. Is there a way
resources can be showed on these bars?

Regards,
Sri
 
J

jkpm1918

choose all tasks then

choose Format > Bar Styles

see "Task" bars and "Critical Task"

To add the Task Name to any of those bars:

click the "Text" tab at the bottom of
the dialog box.

pick up 1 of 5 places you may position information from
fields: Left, Right, Top, Bottom, and Inside.

click in the Left area and from the drop-down select Name from the list
of fields.

finally click OK!
 