A
Akhlaq Khan
I am a newbie and recently started using MS project server. i created a
project plan and assigned tasks to different resources. According to
schedule, the deadline turned to be 21st April 2006. Due to some unavoidable
issues the resources tasks could not complete thier tasks on their assigned
deadline which means the deadline must slip by a few days. Now i want to
calculate the new deadline (estimated deadline) after the slippage. how can
i do that? is there an article that can walk me through it?
thank you,
akhlaq khan.
project plan and assigned tasks to different resources. According to
schedule, the deadline turned to be 21st April 2006. Due to some unavoidable
issues the resources tasks could not complete thier tasks on their assigned
deadline which means the deadline must slip by a few days. Now i want to
calculate the new deadline (estimated deadline) after the slippage. how can
i do that? is there an article that can walk me through it?
thank you,
akhlaq khan.