How to force rebuild and update data from msproject to project server database

  • Thread starter Microsoft Communities
  • Start date
M

Microsoft Communities

Hi all,
(I use MS Project Pro 2003 connect to Project Server)
I have a ms project file (ABC.Published), in this file I have 800 task. In
the project server database, table MSP_TASKS, this project has 800 rows, but
there are 600 rows in the MSP_VIEW_PROJ_TASKS_STD. I forced rebuild data
with this help:
http://www.projectserverexperts.com/ProjectServerFAQKnowledgeBase/BinaryRebuild.aspx
but data in MSP_VIEW_PROJ_TASKS_STD remain 600 rows.

Is there another way to force rebuild MS Project Server Database? I need to
see the log for project server error, where can I see?

Thanks
 
M

Microsoft Communities

I republished the project, but nothing happens :(

Did you already try republishing the project?
Collaborate => Publish => Project Plan
Collaborate => Publish => Republish Assignments

Regards,
Hans


Projectopolis


Microsoft Communities wrote:
Hi all,
(I use MS Project Pro 2003 connect to Project Server)
I have a ms project file (ABC.Published), in this file I have 800 task. In the project server database, table MSP_TASKS, this project has 800 rows, but there are 600 rows in the MSP_VIEW_PROJ_TASKS_STD. I forced rebuild data with this help: http://www.projectserverexperts.com/ProjectServerFAQKnowledgeBase/BinaryRebuild.aspx but data in MSP_VIEW_PROJ_TASKS_STD remain 600 rows.

Is there another way to force rebuild MS Project Server Database? I need to see the log for project server error, where can I see?

Thanks
 