How to get proj tasks re-owned bythe Project Manager in Project Se

D

dtarkington

When a project is initially published in Project Server 2003 the person who
published the project is the Owner/Project Manager yet if someone else opens
the project and changes a task/resource and resaves the project, that task is
then shown with the second person being the project manager for that task.
How do I get the tasks back to being under the original owner/project manager?
 
M

Matt Stevenson (UK)

Get the original PM to open the plan, and use Collaborate > Re-pulish
Assignments and select the "become manager of these assigments" option.
 