Hugues Perron
Hi,
We are using MS Project server 2003, and the resources pool.
In MS Project, when I want to see the workload for the resources I use the
"Resources usage" view. This is fine to see the general workload of each
resource because it includes the assignments for all other projects the
ressources are assigned to. But I would like to see the resources workload
for the current projet. I haven't find the way to display the assignement
for the current project only. I could use a filter, but the rollup total for
the resource remains the same.
Is there a way to display the assignments for the current project only (I
don't want to use the portfolio, it must be in MS Project).
Thanks
Hugues Perron
We are using MS Project server 2003, and the resources pool.
In MS Project, when I want to see the workload for the resources I use the
"Resources usage" view. This is fine to see the general workload of each
resource because it includes the assignments for all other projects the
ressources are assigned to. But I would like to see the resources workload
for the current projet. I haven't find the way to display the assignement
for the current project only. I could use a filter, but the rollup total for
the resource remains the same.
Is there a way to display the assignments for the current project only (I
don't want to use the portfolio, it must be in MS Project).
Thanks
Hugues Perron