how to keep settings filter the tasks

M

Micheal

Hi,

I want that when the project manager open any project in project
professional 2003 then project only show incomplete tasks . what settings i
need to do in global template .
pls reply me soon

regards
micheal
 
D

Dale Howard [MVP]

Micheal --

You cannot control this in the Enterprise Global file, at least not
directly. However, you can create an enterprise custom View that includes
the Incomplete Tasks filter in the defintiion of the view and then place
this View in the Enterprise Global file. From there, you will need to teach
your PM's to apply this view. Hope this helps.
 