P
PP
Hi all,
In project 2007:
In PWA
Resources saved and published their tasks with the actual work
Project Manager accept all the task updates.
How will the project manager know which project he needs to republish in
order to have the latest data in the different views of PWA
How will he know which projects have no new actuals, and so don't need to be
republished.
Should he open every single project in Project Professional and see if he
gets a message that the project plan has been updated?
Any other less time-consuming solution?
Thanks in advance
PP
In project 2007:
In PWA
Resources saved and published their tasks with the actual work
Project Manager accept all the task updates.
How will the project manager know which project he needs to republish in
order to have the latest data in the different views of PWA
How will he know which projects have no new actuals, and so don't need to be
republished.
Should he open every single project in Project Professional and see if he
gets a message that the project plan has been updated?
Any other less time-consuming solution?
Thanks in advance
PP