How to reflect resource on vacation

A

Aravind G

Hi,

I use MS Project 2007. I wish to know the best way to represent when a
resource will be on vacation for a particular day(s) in my schedule. Can
anyone throw some light on this please? If you give an example that would be
great. Thank you in advance.
 
R

Rod Gill

Hi,

Edit the Resource's calendar and set the vacation days to non-working.
Tools, Change Working time.

--

Rod Gill
Microsoft MVP for Project

Author of the only book on Project VBA, see:
http://www.projectvbabook.com




Aravind G said:
Hi,

I use MS Project 2007. I wish to know the best way to represent when a
resource will be on vacation for a particular day(s) in my schedule. Can
anyone throw some light on this please? If you give an example that would
be
great. Thank you in advance.

--

Thanks and Regards,
Aravind G

__________ Information from ESET Smart Security, version of virus
signature database 4674 (20091209) __________

The message was checked by ESET Smart Security.

http://www.eset.com

__________ Information from ESET Smart Security, version of virus signature database 4674 (20091209) __________

The message was checked by ESET Smart Security.

http://www.eset.com
 
V

vanita

Hi Aravind

Adding on to Rod's suggestion. If you want to identify the non working day
as a vacation. In 'Exceptions' tab of 'Change working time' window for that
non working day you may write that it is for the vacation.

I hope it helps.
Vanita
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top