I want to know how to remove constraint in Task
J José Miguel Piñeres Oct 13, 2009 #2 Hi, Double click on the task, select the "Advanced" tab, on the list "constraint type" select the option "As soon as possible". Click OK. I hope this helps. Best regards,
Hi, Double click on the task, select the "Advanced" tab, on the list "constraint type" select the option "As soon as possible". Click OK. I hope this helps. Best regards,
J Jack Dahlgren MVP Oct 13, 2009 #3 Double-click the tasks. In the task information dialog box, select the "Advanced" tab Set the Constraint Type to "As Soon As Possible" -Jack Dahlgren
Double-click the tasks. In the task information dialog box, select the "Advanced" tab Set the Constraint Type to "As Soon As Possible" -Jack Dahlgren
M Michael.Tarnowski Oct 14, 2009 #4 I want to know how to remove constraint in Task Click to expand... Hi, if you need to remove a constraint that you set earlier, use ASAP in case of forward scheduling, and ALAP in case of backward scheduling. Hope that helps Cheers Michael
I want to know how to remove constraint in Task Click to expand... Hi, if you need to remove a constraint that you set earlier, use ASAP in case of forward scheduling, and ALAP in case of backward scheduling. Hope that helps Cheers Michael
J Jim Aksel Oct 16, 2009 #5 Jack and Jose have perfect answers. If constraints appear on many tasks, you may also consider inserting the "Constraint Type" field and you may find it is faster to change it there. -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com
Jack and Jose have perfect answers. If constraints appear on many tasks, you may also consider inserting the "Constraint Type" field and you may find it is faster to change it there. -- If this post was helpful, please consider rating it. Jim Aksel, MVP Check out my blog for more information: http://www.msprojectblog.com