How to remove link between percentage complete and remaining dura.

  • Thread starter link between percentage complete and rem
  • Start date
J

John

link between percentage complete and rem <link between percentage
complete and (e-mail address removed)> wrote:


rem,
Percent complete and duration in Project are properties of the task
object - they cannot be "unlinked". There may be more to an answer for
you but without any kind of explanation (i.e. you only posted a title),
we have no idea what you are trying to do.

John
Project MVP
 
C

Catfish Hunter

The only thing I can tinnk of is under Tools>Options>Calculation. Threre are
a few choices there.
 
S

Steve House [Project MVP]

Since "% Complete" refers to duration by definition, it is impossible to
unlink them. It explicitly indicates the portion of the total duration that
has been worked to date. [% Complete]=100 *
[ActualDuration]/[TotalDuration] and
[RemainingDuration]=[TotalDuration]-[Actual Duration], therefore Remaining
Duration will always be related to % Complete. Perhaps you are confusing %
Complete with % Work Complete or % Physical Complete - the three different
percentages represent three different concepts and measurements of progress.
When you say a task is 50% complete you need to be totally clear on just
what kind of progress you're looking at - time, effort, or output.
--
Steve House [MVP]
MS Project Trainer & Consultant
Visit http://www.mvps.org/project/faqs.htm for the FAQs


"link between percentage complete and rem" <link between percentage complete
and (e-mail address removed)> wrote in message
news:[email protected]...
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top