How to remove weekends (Sat & Sun) in Project?

C

conks

Hi,

I need to remove weekends in my Gantt Chart and show working days onl
(Mon - Fri).

How can you do this in Project?

Thanks
 
J

JulieS

Hello conks,

Welcome to the Project newsgroup. Sorry, you cannot hide the
display of Saturday and Sunday in the Gantt chart view. You can
show a "5 day" week in the Calendar view.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
D

djgodard

How do you show 5 day work week?

Hello conks,

Welcome to the Project newsgroup. Sorry, you cannot hide the
display of Saturday and Sunday in the Gantt chart view. You can
show a "5 day" week in the Calendar view.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
T

The Project Management Workshop

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top