M
Mike
Hello,
I'm wondering how to factor in shipping times into my schedule.
Currently I make a resource called UPS and then give it the same
working hours per day as the default set in Tools, Options, Calendar,
with non-working weekends. I noticed that if a day = 8 hours and I
say that UPS works 8 hours during the day, the schedule will show that
UPS finishes its task (i.e, ships and delivers a package) at the end
of a day, instead of the next day. So right now I am setting the
schedule such that shipping a package via UPS overnight requires 1.1
days, 2nd-day requires 2.1 days, etc... (the whole point is to avoid
counting weekends, which elapsed time counts). Is there a
better/cleaner way of handling this?
Thanks,
Mike
I'm wondering how to factor in shipping times into my schedule.
Currently I make a resource called UPS and then give it the same
working hours per day as the default set in Tools, Options, Calendar,
with non-working weekends. I noticed that if a day = 8 hours and I
say that UPS works 8 hours during the day, the schedule will show that
UPS finishes its task (i.e, ships and delivers a package) at the end
of a day, instead of the next day. So right now I am setting the
schedule such that shipping a package via UPS overnight requires 1.1
days, 2nd-day requires 2.1 days, etc... (the whole point is to avoid
counting weekends, which elapsed time counts). Is there a
better/cleaner way of handling this?
Thanks,
Mike