I have a custom Enterprise field defined for Timesheet View. After
plan publishing in PWA it's shown properly for tasks of the lowest
outline level - they are assigned to resources. However, it's empty
for summary tasks - they are not assigned to anyone.
For example, I have following tasks:
Issue - Description - not assigned to resource
Work Order 1 - assigned to resource
Work Order 2 - assigned to resource
Work Order 3 - assigned to resource
In PWA the custom field is filled for Work Order tasks, but empty for
Issue. As I understand this is because summary tasks have no
assignments and would not publish all information.
Is there any way to display Enterprise fields for summary tasks in
Timesheet View for PWA?
Thank you,
Igor.
I have a custom Enterprise field defined for Timesheet View. After
plan publishing in PWA it's shown properly for tasks of the lowest
outline level - they are assigned to resources. However, it's empty
for summary tasks - they are not assigned to anyone.
For example, I have following tasks:
Issue - Description - not assigned to resource
Work Order 1 - assigned to resource
Work Order 2 - assigned to resource
Work Order 3 - assigned to resource
In PWA the custom field is filled for Work Order tasks, but empty for
Issue. As I understand this is because summary tasks have no
assignments and would not publish all information.
Is there any way to display Enterprise fields for summary tasks in
Timesheet View for PWA?
Thank you,
Igor.