Can anyone tell me how to submit the timesheet for myself
in project pro 2003.
is it just update all the tasks and press the "update all"
button?
What if i hvnt updated all items in the reporting period ?

Thx in advance
 
D

Dale Howard [MVP]

Jackei --

When you are ready to update progress to your project manager, you can
simply click the Update All button. If you are not ready to update all of
the tasks for which you have entered actuals, then select the tasks you are
ready to update and click the Update Selected Tasks button. When you are
entering actual progress during the week, you can click the Save Changes
button at the end of each day to save the changes to the Project Server
database. Hope this helps.
 
G

Guest

Thx Dale
-----Original Message-----
Jackei --

When you are ready to update progress to your project manager, you can
simply click the Update All button. If you are not ready to update all of
the tasks for which you have entered actuals, then select the tasks you are
ready to update and click the Update Selected Tasks button. When you are
entering actual progress during the week, you can click the Save Changes
button at the end of each day to save the changes to the Project Server
database. Hope this helps.







.
 