How to update an activity plan in PWA 2007

M

MFJ

Hello,

I created an activity plan, assigned myself to a task and published the plan.

In my timesheet: I log time, submit and approve (automatically by the
system). The plan is not updated in the project center.

In my tasks: I see the task but cannot modify actual work, remaining work,
%complete or %work complete. If I click on the task, a new window opens but
everything is grayed. If I try to import the timesheet, the import window
opens but there is no data to import.

What am I doing wrong? (All permissions are set to "allowed")
 
A

AKZ

Hi

I and my team have the same problem. We are unable to import timesheets to
update our schedule. I hope someone can provide a solution.
 
P

PeteK

Gary,

I thought Activity plans were designed for small projects that don't need
all the capabilities of a bonifide project. I thought Proposals were
designed for determining demand.

Please correct me if I'm wrong because I was planning on capturing actuals
in activities.

Thanks,
PeteK
 
G

Gary L. Chefetz [MVP]

Sorry you are correct, I was thinking proposals.

--

Gary L. Chefetz, MVP
MSProjectExperts
For Project Server Consulting: http://www.msprojectexperts.com
For Project Server FAQS: http://www.projectserverexperts.com


PeteK said:
Gary,

I thought Activity plans were designed for small projects that don't need
all the capabilities of a bonifide project. I thought Proposals were
designed for determining demand.

Please correct me if I'm wrong because I was planning on capturing actuals
in activities.

Thanks,
PeteK
 
A

anovaktx

If you had two small projects, would you create two separate activity
plans, or create one activity plan for small projects and enter each
one of them as a task?

Thanks,
Andy
 