How to Update Task Progress in Project Web Access

A

Ashish kanoongo

Hello
How to Update Task Progress in Project Web Access without opening Project Professional 2007?

Ashish
 
D

Dale Howard [MVP]

Ashish --

Assuming that your team members have submitted task updates to you, simply
click the "Task Updates" link in the Quick Launch menu and approve task
progress. Hope this helps.





Hello
How to Update Task Progress in Project Web Access without opening Project
Professional 2007?

Ashish
 
A

Ashish kanoongo

Hello Dale

Thanks for reply.

It seems I have not explained properly. Actually My PM wants to update task
progress i.e. in percentage (%) or in Hours himself.

he published a project on project server with assigned task and from PWA he
want to update task progress.

We are using Project 2007 using MOSS 2007.

Ashish
 
D

Dale Howard [MVP]

Ashish --

The only way for the PM to manually update the status of a project is to
open it in Project Professional 2007 and then enter progress information,
such as an Actual Start date, % Complete, Actual Work, etc. I'm not sure
why the PM is resisting doing so. He has Project Professional 2007, right?
Hope this helps.
 