How to use Early (Start/Finish) and Late (Start/Finish)

J

jp

Hi,

I've seen these columns but can't manually change them.

How are these fields used in MS Project 2003?

Thank you.

-jaime
 
J

Jack Dahlgren MVP

They are calculated by Project. If a task is on the critical path they will
be the same. If there is slack, it will be equal to the difference between
the two.
The slack is the amount that the task can be delayed before it affects the
end date of the project.

-Jack Dahlgren
 
J

jp

Oh ok. This is system based and it is calculated based on the Slack.
I was thinking that one could go and set that up manually.
Thank the reply Jack.

-jaime
 