how to view project calendar in working days report

C

claudette

I have created a project calendar and would like to see the working times and
exceptions in the Working Days report. Can anyone tell me how this is done?
 
J

JulieS

Hello Claudette,

The Working Days report is under the Overview Reports grouping. In
Project 2003 View > Reports > Overview. Project 2007 is Report >
Reports > Overview.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 