B
Bug Eyed
Hi all.
I've inherited a huge MSProject file to clean for upload into a time
tracking system.
The file has roughly 730 resources... While this may not seem big to you,
it's enormous to me. Of those resources, probably 250 are
duplicates/typos/and other manglings of resources that already exist in the
plan.
My question is simple: Is there an easy way to take a block of tasks
(listed by resource under RESOURCE USAGE) and quickly re-assign them to
another resource in the project?
Another way to state the problem might be to say is there a way to 'merge'
the assignments and information (no time entered, yet) for two similar
resource - Jim.A.Beam and James.A.Beam, for example?
Thanks, Bug Eyed
I've inherited a huge MSProject file to clean for upload into a time
tracking system.
The file has roughly 730 resources... While this may not seem big to you,
it's enormous to me. Of those resources, probably 250 are
duplicates/typos/and other manglings of resources that already exist in the
plan.
My question is simple: Is there an easy way to take a block of tasks
(listed by resource under RESOURCE USAGE) and quickly re-assign them to
another resource in the project?
Another way to state the problem might be to say is there a way to 'merge'
the assignments and information (no time entered, yet) for two similar
resource - Jim.A.Beam and James.A.Beam, for example?
Thanks, Bug Eyed