M
maharg
Hi,
I'm using MS project 2007. We have a central resource plan of which all
project plans use. Within this we keep individuals holidays up to date
(tools>change working time>"person a">add an exception).
Is there a way to make these holidays clearer in the resouce usage
view?
Exceptions from the standard (project calendar) (national holidays,
weekends etc) block out each day in the resource usage view by greying
out the day. Exceptions for "A.N Other" leave the day as white (but as
expected dont allow any work to be scheduled for those days). Is it
possible to make the resource usage view highlight resource execptions
in the same way plan exceptions are?
This would make it clearer in identfying when a resource is not
available as apposed to when a resource is under allocated.
Thanks,
Graham.
I'm using MS project 2007. We have a central resource plan of which all
project plans use. Within this we keep individuals holidays up to date
(tools>change working time>"person a">add an exception).
Is there a way to make these holidays clearer in the resouce usage
view?
Exceptions from the standard (project calendar) (national holidays,
weekends etc) block out each day in the resource usage view by greying
out the day. Exceptions for "A.N Other" leave the day as white (but as
expected dont allow any work to be scheduled for those days). Is it
possible to make the resource usage view highlight resource execptions
in the same way plan exceptions are?
This would make it clearer in identfying when a resource is not
available as apposed to when a resource is under allocated.
Thanks,
Graham.