Resource Usage View Rolled Up

K

Kirsten

I need to have the Resource Usage View Rolled Up by Summary Task. Which in
turn would hide the resource tasks. I am ultimately need a report/view that
shows Project by Resource by Monthly Work Hours.

Is this possible?

Thanks,
Kirsten
 
J

JulieS

Hi Kirsten,
Add the "Task Summary Name" field to the Resource Usage view.
Create a custom group to group by Task Summary Name Assignment
field, then by Name.

Does that get you close?

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 
K

Kirsten

I have playing with creating a custome group with the Task Summary Name being
the first field and then by Name, but it's not grouping the Task Summary at
all. I am not sure what I am missing.
 
K

Kirsten

I keep getting Task Summary Name: No Value.

Kirsten said:
I have playing with creating a custome group with the Task Summary Name being
the first field and then by Name, but it's not grouping the Task Summary at
all. I am not sure what I am missing.
 
J

JulieS

Kirsten,

Make sure in the group box you click the checkbox for "group
assignments not resources". In the Task Summary name field in
the group box, select "Assignment" for the field type.

I hope this helps. Let us know how you get along.

Julie
Project MVP

Visit http://project.mvps.org/ for the FAQs and additional
information about Microsoft Project
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top