Hyperlinks

M

Missy

Hi

You know how you can insert hyperlinks in MS Project 2003 so an icon appears
in the 'Information' column, can you insert them on PWA, or how do you
display this if it has been inserted in MS Pro?

Thanks
 
G

Gary L. Chefetz [MVP]

Missy:

In PWA, add the HREF field to a task view to both see and use the link from
PWA.
 
M

Missy

Hi Gary,

Thanks for the reply.

I inserted a hyperlink in Project by Insert > Hyperlink.

I have added a column "Hyperlink Href" in 'View My Tasks' view and
'Resources Summary' View but nothing is showing up.

Do you know what I have done wrong?
 
G

Gary L. Chefetz [MVP]

Missy:

The Resource summary view is a "resource" view. This will never show task
level detail. It only displays resource information. The View My Tasks view
is the Timesheet view. In order to add a field to this particular view, you
need to take quite a few steps that outlined in the following FAQ:

http://www.projectserverexperts.com/Shared Documents/changetimesheet.htm

You should try adding the field to a project task view that you reach from
the Project Center. You may need to republish your project to push the
information into Web Access.
 
Top