O
owp^3
We have deployed Project Server and use Project Professional throughout the
enterprise.
A single instance of Project Professional shows seconds when totalling
resource assignments values in Resource Usage View. The task levels show
hours: its just the totals for the resource that look like 678,000s.
We tried to uninstall and reinstall the application. But the behaviour
remains.
HOW DO WE TURN IT OFF?
Thanks,
enterprise.
A single instance of Project Professional shows seconds when totalling
resource assignments values in Resource Usage View. The task levels show
hours: its just the totals for the resource that look like 678,000s.
We tried to uninstall and reinstall the application. But the behaviour
remains.
HOW DO WE TURN IT OFF?
Thanks,