H
HCLIFF
Using a customized Resource sheet, my company builds up a time phased project
budget based upon generic resources. e.g for resource A we have forecasted
40hrs/month for Oct, Nov, & Dec. We've developed 2 custom fields: Total
Forecasted Hrs & Work Remaining (Total Forecasted/(work/60)). Resource A has
120 hrs for Both fields. When I assign the generic resource to Task 1A for
10 hrs; Total Forecasted =120, but Remaining is 110 (work is now 10hrs).
When I substitue a Person for the Resource A on Task 1A, total Forecasted and
Remaining fields return to 120hrs (not what we wanted). Bottomline, the
generic resource is just a bucket of hours. Is there a way, as enterprises
resources are assigned, that the generic resource hours decrease?
Thanks
budget based upon generic resources. e.g for resource A we have forecasted
40hrs/month for Oct, Nov, & Dec. We've developed 2 custom fields: Total
Forecasted Hrs & Work Remaining (Total Forecasted/(work/60)). Resource A has
120 hrs for Both fields. When I assign the generic resource to Task 1A for
10 hrs; Total Forecasted =120, but Remaining is 110 (work is now 10hrs).
When I substitue a Person for the Resource A on Task 1A, total Forecasted and
Remaining fields return to 120hrs (not what we wanted). Bottomline, the
generic resource is just a bucket of hours. Is there a way, as enterprises
resources are assigned, that the generic resource hours decrease?
Thanks