R
Roland
I am using a macro to consolidate multiple schedules into a single IMS. When
the macro completed, I noticed about half the resources contained 0 hours in
the summary work but contains work on their assigned tasks. MSP identified
some resources as being overallocated even with 0 hrs. I am using MSP 2007
and Calculation = Automatic.
Example:
Named Resource 0 hrs (should equal 30)
Task 1 10 hrs
Task 2 20 hrs
Any suggestions as to why some resources work fine but others don't?
the macro completed, I noticed about half the resources contained 0 hours in
the summary work but contains work on their assigned tasks. MSP identified
some resources as being overallocated even with 0 hrs. I am using MSP 2007
and Calculation = Automatic.
Example:
Named Resource 0 hrs (should equal 30)
Task 1 10 hrs
Task 2 20 hrs
Any suggestions as to why some resources work fine but others don't?