I wanna get physical

D

dave

I want to publish the "physical complete" field available in the tracking
gantt table to the Server. How is this accomplished?

Dave
 
D

Dale Howard

Dave --

I may have some bad news for you. The Physical % Complete field is not
available in Project Web Access in either Project Center or Project views.
Sorry.

--
Dale A. Howard
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
D

Dale Howard

Dave --

I don't know. I don't work for Microsoft, so I can't even speculate on why
the Physical % Complete field is not available in either the Project Center
or Project views in PWA. Anybody else know?

--
Dale A. Howard
Enterprise Project Trainer/Consultant
Denver, Colorado
http://www.msprojectexperts.com
"We wrote the book on Project Server"
 
D

Dani

Dani --

I think that Microsoft must have left the field name off the list of
available fields in the 'Manage Views' section of the PWA Admin Site,
HOWEVER, I have found a workaround:
- create a task level (and/or) project level Custom Enterprise Field
in Project Professional, and for the Formula value, insert the
'Physical % Complete' field
- add the custom enterprise field to the appropriate project views
(for the task level field) and/or project centre views (for the
project level field)
 
Top