I want to "Reverse" baseline

B

boggyboy

When baselining, project moves timephased work into timephased baseline work.
I would like to go the other direction. Is that possible?
 
J

Jan De Messemaeker

Hi,

Yes.
You can write a procedure reading all tasks, then all assignments for each
task, get the timephasedvalues for each assignment's work and baseline work,
loop through the timescaledvalues to copy baselinework into work.
Hope this helps,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
Top