if you are re-painting a retirement village and you want to track for each
residence how much paint is needed / used - you can add the paint in as a
'material' resource, with a material label of the unit you measure (buy) the
paint in (ie litres) and a standard cost of one of those units. then when
you're setting up your project you can nominate how much paint you think
you'll need in each paint residence task (e.g. 15 - project will change
this to 15 litres) and then you can track the actuals as well.