If not using outlook. How do tea members report time.

J

Jay

Maybe a newb question but if we weren't using outlook how do you have team
members report time. Do you lose that functinality unless you adapt project
to an external time system.
 
E

Earl Lewis

Jay,

If you're using project server you have them login to project web access and enter time in the timesheet view. If you're not using project server you need to work out a process where team members update/notify the project manager on work completed and the project manager can update the plans.

Earl
Maybe a newb question but if we weren't using outlook how do you have team
members report time. Do you lose that functinality unless you adapt project
to an external time system.
 