ignoring nonworking days

E

engineer hussam

please inform me how can i ignor the nonworking days in the microsoft project
thanks
 
J

Jeanders

In the duration column you can input the duration as elapsed days. As an
example if you wanted the task to run 7 consecutive days you would input...
7ed.
 
C

Chris Marriott

Hi

You can create a calendar template and set all days as working (define the
hours to suit)

You can use this calendar as a project calendar
Go to Project > Project Information and select the calendar from the drop down

However, this will only suffice until you assign resources and then their
calendars will over ride that setting

Alternatively, apply the new calendar to one or more tasks...

Double click the task and go to the advanced tab

Select the new calendar and tick the "scheduling ignores resource calendars"
box

This will enforce the new calendar settings with or without resources
assigned.

I hope this helps
--
Regards


Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer
 
M

Mike Glen

Hi Chris,

Welcome to this Microsoft Project newsgroup :)

If you mean not showing nonworking time on the Gantt Chart calendar, then
you can't. Sorry :(

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for Project Tutorials
 