Hi
You can create a calendar template and set all days as working (define the
hours to suit)
You can use this calendar as a project calendar
Go to Project > Project Information and select the calendar from the drop down
However, this will only suffice until you assign resources and then their
calendars will over ride that setting
Alternatively, apply the new calendar to one or more tasks...
Double click the task and go to the advanced tab
Select the new calendar and tick the "scheduling ignores resource calendars"
box
This will enforce the new calendar settings with or without resources
assigned.
I hope this helps
--
Regards
Chris Marriott - PMP MCSE MCDBA
UK - EPM Consultant & Trainer