D
Desmond
I have taken over a schedule on which resources have so far been assigned at
the lowest task level. In order to be able to accurately tie Actual Hours to
the work done in the schedule without requiring team members to enter hours
for each and every task, I propose to assign resources at the Work Package
level from now on. The question I have is whether having resources assigned
at the lowest task level for tasks up to the end of January and having them
assigned at the WP (Summary) level from now on will present problems for MS
Project in rolling totals up to the higher (Control Account) and project
summary levels.
the lowest task level. In order to be able to accurately tie Actual Hours to
the work done in the schedule without requiring team members to enter hours
for each and every task, I propose to assign resources at the Work Package
level from now on. The question I have is whether having resources assigned
at the lowest task level for tasks up to the end of January and having them
assigned at the WP (Summary) level from now on will present problems for MS
Project in rolling totals up to the higher (Control Account) and project
summary levels.