impact of putting resource holidays in the microsoft project server

G

gmanchelle

Hi,

I would like to know how and what is the impact of putting
holidays for resources on the MS Project server when using
entreprise calendars.
 
D

Dale Howard [MVP]

gmachelle --

When you add working time to a resource's calendar in the Enterprise
Resource Pool, and then save the pool, Project Server will automatically
reschedule any task in any project to which the resource is assigned during
the nonworking time period you enter. The next time a project manager opens
an impacted project, he/she will see yellow envelope indicators to the left
of any tasks that were rescheduled due to the nonworking time for the
resource. Hope this helps.
 
Top