mike
Hello, I have a client whom I am in the process of discussing pros /
cons of using an administrave MPP file vs the admin categories.
If they use the admin project file and assign someone to task
vacation, in order for it to appear on thir timesheet it should the
resource be assigned to the fixed duration task w/ a constraint on it
to end Dec 31 at 0% units. I though in reading past posts, assinging
someone to a task like this at 0% and some negaive impact on
avaialbilty, but I could be mistaken.
Again I am just weighing the pros and cons. I am a advocate of Admin
Categories for time off, since but the cleint is locked in on the O%
assinment task.
Any input would be appreciated.
cons of using an administrave MPP file vs the admin categories.
If they use the admin project file and assign someone to task
vacation, in order for it to appear on thir timesheet it should the
resource be assigned to the fixed duration task w/ a constraint on it
to end Dec 31 at 0% units. I though in reading past posts, assinging
someone to a task like this at 0% and some negaive impact on
avaialbilty, but I could be mistaken.
Again I am just weighing the pros and cons. I am a advocate of Admin
Categories for time off, since but the cleint is locked in on the O%
assinment task.
Any input would be appreciated.