Hi,
I'd like people to report actual worked hours in Excel format so I can then
merge it into the MSP file. I know how to export the project tasks with
assignment rows to Excel. But how do I re-import it into the project? The
exported Excel file contains IDs for tasks and resources and the import
process does not seem to differentiate them; it interpretes a resource ID as
a task ID.
Thanks,
Jacques D.