Troy
We are converting from Project 2000 to Project Server 2003
We have numberous projects in progress with existing actual work
We want to be able to load the existing projects with the existing actual work into Project Server 2003 and then begin using Task Timesheets and update the already in-progress projects from PWA and Project Server 2003
However, when i import an existing project with existing actual work, i keep getting the out-of-synch with actual work error. If i keep selecting 'no' to the window, then the actuals remain. When i accept 'yes' the existing actual work is made to 0hours
How do I get around the out-of-sync actuals temporarily to load existing projects and then begin using Project Server 2003
thx.
We have numberous projects in progress with existing actual work
We want to be able to load the existing projects with the existing actual work into Project Server 2003 and then begin using Task Timesheets and update the already in-progress projects from PWA and Project Server 2003
However, when i import an existing project with existing actual work, i keep getting the out-of-synch with actual work error. If i keep selecting 'no' to the window, then the actuals remain. When i accept 'yes' the existing actual work is made to 0hours
How do I get around the out-of-sync actuals temporarily to load existing projects and then begin using Project Server 2003
thx.