Import Project Plan - Local/Map to enterprise resource

D

DV

Hello ALL,
When I import my project plan using the Import Wizard and
I use
1) Keep Local With Base Calendar - My Project Plan
Uploads fine. I do have to rename 3-4 resources whose
name is similar to the name in my Enterprise Resource
Pool.

2) Map Resource to Enterprise Resource - My Project Plan
does upload BUT the duration of the Project Plan changes.
I was thinking that this is an issue with the calendar
but I dont know what is the Problem now. I do have a copy
of same Project Plan in the database...Cud that be the
Reason.

Thank you in advance,
DV.
 
D

Dale Howard

DV --

I would suspect that your problem stems from the fact that your enterprise
resource calendars are different than the resource calendars used when you
keep the resources local. It sounds like you need to do some "synching up"
of your calendars to solve this problem. Examine the two sets of calendars
and look for the differences between them. Hope this helps.
 