D
DV
Hello ALL,
When I import my project plan using the Import Wizard and
I use
1) Keep Local With Base Calendar - My Project Plan
Uploads fine. I do have to rename 3-4 resources whose
name is similar to the name in my Enterprise Resource
Pool.
2) Map Resource to Enterprise Resource - My Project Plan
does upload BUT the duration of the Project Plan changes.
I was thinking that this is an issue with the calendar
but I dont know what is the Problem now. I do have a copy
of same Project Plan in the database...Cud that be the
Reason.
Thank you in advance,
DV.
When I import my project plan using the Import Wizard and
I use
1) Keep Local With Base Calendar - My Project Plan
Uploads fine. I do have to rename 3-4 resources whose
name is similar to the name in my Enterprise Resource
Pool.
2) Map Resource to Enterprise Resource - My Project Plan
does upload BUT the duration of the Project Plan changes.
I was thinking that this is an issue with the calendar
but I dont know what is the Problem now. I do have a copy
of same Project Plan in the database...Cud that be the
Reason.
Thank you in advance,
DV.