F
franklin
I am going through the process of importing an existing local project into
Project Server 2007. I fixed the local calendars to refer to an enterprise
calendar. Still, at step 4 of the Import Project Wizard it says "The Project
contains ... Number of errors 5", even though there are no errors noted in
the "Errors" column. What could possibly constitute these 5 errors? Is
there anything specific I need to look out for? (I don't have any resources
in the project)
Input would be much appreciated.
Project Server 2007. I fixed the local calendars to refer to an enterprise
calendar. Still, at step 4 of the Import Project Wizard it says "The Project
contains ... Number of errors 5", even though there are no errors noted in
the "Errors" column. What could possibly constitute these 5 errors? Is
there anything specific I need to look out for? (I don't have any resources
in the project)
Input would be much appreciated.