When I attempt to import a project to enterprise, I am forced to select
"Standard Calendar" as the base calendar for this schedule. My schedule uses
a different base schedule which is built into the schedule called "My
Calendar". I need to, but cannot import the "My Calendar" along with the
project which in turn by selecting the standard calendar causes numerous
tasks' dates to change by one day. Is there a way to force Project to
recognize "my calender" as the "standard" calender, as the entire
organization uses the same calender, not the "standard" Project calender?

Also, is there a fix to allow more than one PM read/write access to the
entire schedule? I have 4-5 PM's that would like to be able to read/write to
the entire schedule?

Thanks !!

Scott
 
G

Gary L. Chefetz \(MVP\)

Scott:

You have two choices: Ask your Project Server administrator to set Project
Server to allow local base calendars, or create a corresponding Enterprise
Calendar before importing your project.

--

Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com

-
 
S

scott

Thanks Gary!! Will give it a try.



Gary L. Chefetz (MVP) said:
Scott:

You have two choices: Ask your Project Server administrator to set Project
Server to allow local base calendars, or create a corresponding Enterprise
Calendar before importing your project.

--

Gary L. Chefetz, MVP
"We wrote the books on Project Server"
http://www.msprojectexperts.com

-
 