Is it possible to import an existing Project Calendar to create a new Enterprise Calendar?
J Jerry L. Welch Mar 19, 2010 #1 Is it possible to import an existing Project Calendar to create a new Enterprise Calendar?
J Jerry L. Welch Mar 19, 2010 #2 I answered my own question... Open a file with the calendar you want to import, goto 'change working time' there is a button (if correctly configured and connected to Project Server) to "Import into Enterprise Calendar"
I answered my own question... Open a file with the calendar you want to import, goto 'change working time' there is a button (if correctly configured and connected to Project Server) to "Import into Enterprise Calendar"