Importing from an Excel file

J

joshroberts

I'm trying to import project data from an Excel file into MS Project 2000.
It works fine except a small problem with the predecessors field. In one of
the cells the desired value is "7,28" which is written correctly in the excel
file but when imported it reads "7,51" and creates a task 51 to link it to.
The project should be only 30 tasks long. I'm very confused so any help will
be appreciated. Thanks.

Josh
 