Importing Project - Data Mixup

V

V

I am importing a project (local mpp file) into server
2003.
We have a Resource T-Docs view in the local mpp file.

After importing, the T-Docs data gets mixed up. For
example, I have 8 hrs entered for each day from Monday -
Friday for a given resource. After publishing it onto the
server, I get the following as hours entered from Monday
through Friday - 7.78, 8.28, 8.2, 8.12, 8.1

What is the cause of this and how to fix it?

Appreciate your help.
V
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top