G
Graham
A project that contained customizations to the standard calendar was
imported to Project 2002 Server, which is set to allows local base
calendars.
The project contained changes to the 'standard' calendar, for example
Christmas to new years was booked off.
When the project was opened from MS Project 2002 Server the calendar
changes were in effect, however there was no way to view or modify
those custom changes. The 'Standard' calendar after the import does
not show the custom changes.
I would have expected a definite conflict between the calendars as the
global calendar is called 'Standard' and the modified local calendar
is called 'Standard' as well.
Any insight to this problem would be appreciated.
Thanks,
Graham
imported to Project 2002 Server, which is set to allows local base
calendars.
The project contained changes to the 'standard' calendar, for example
Christmas to new years was booked off.
When the project was opened from MS Project 2002 Server the calendar
changes were in effect, however there was no way to view or modify
those custom changes. The 'Standard' calendar after the import does
not show the custom changes.
I would have expected a definite conflict between the calendars as the
global calendar is called 'Standard' and the modified local calendar
is called 'Standard' as well.
Any insight to this problem would be appreciated.
Thanks,
Graham