Hi Lily,
I guess I'm still not following -- what is in your template that the Project
Manager's are omitting? Would you not be better off just modifying their
project plan with the additional information/details you need?
You can *insert* a project into an existing project that is based upon your
template through Insert > Project. When you insert a project, it copies all
data from the inserted project into the existing project and, by default,
maintains a link to the original project file. If the original project file
is modified, you will see your project file update.
If you have custom views, tables, fields etc, you can copy the defintions of
the customization from your template into the Project Manager's project
through Tools > Organizer. Open a project based upon your template and then
open the PM's project file. You can copy the definitions as needed.
I hope this helps.
Julie