In Project 2007 how do I set non default working time

L

lynnes

In earlier versions of Project I could click on Tools/Change Working Time,
then click on a non working day - say Saturday 4/4/09 - click the radio
button for "Non default working time" & then click on OK & Project would make
Saturday, 4/4/09 a working day (& leave the rest of my calendar alone). Now
I have Project 2007 & when you click on Tools/Change Working Time, the option
for "Non default working time" is no longer there. So how do I turn one
Saturday into a working day for my whole project without having to create
special calendars, resource calendars, task calendars, etc.
 
J

Jack Dahlgren

Go to the change working time dialog. In the bottom half of the form, enter a
name for the exception and then click the "details" button to set how project
is going to treat it. You have a lot more options and can make that one day
or every saturday non-default working time. Having the named exceptions makes
it much easier to keep track of them and delete them if necessary.

-Jack Dahlgren
 