In PWA: Work Field unit in Days

A

AV

Is it possible in Tasks from Project Web Access to display the "Actual Work" and "Remaining Work" unit in days, instead of default hours?
 
S

Sainath

Yes.This can be done.When you enter the duration, enter it as "1d" where d represents "day". Project converts it into hours accordingly.
 
C

Chris

Can PWA show days as the default instead of hours? Everything is set up for days in the project file, but PWA is showing hours.
 