When using Project Web Access in Project Server 2003, if the method of
reporting progress in Actual Work and Remaining Work, % work complete updates
correctly when Actual Work is entered, but when Remaining Work is increased,
there is no change in either duration or % Work Complete. Why is this the
case? Can anything be done so that Updates to Remaining Work result in % work
complete = (Actual Work)/(Actual Work + Remaining Work) with similar effects
to duration?