Inactivating Resource (MSPS2003)

R

RandyK

I want to inactivate resources who are no longer with the organization. Is
there anything beyond what is listed below that I need to do?

* Change any work remaining on projects to zero (0)
* IKn the "Build Team From Enterprise" scfreen - Set the Booking Value for
the Resource to Proposed

Anything else?
 
C

Crook

Hi Randy,

As admin, what I do is inactivate the resource in PWA on the admin page.
Then Project Pro 2003 alerts each PM who planned work for that resource that
there is work pending for an inactive resource whenever a project containing
that resource is opened. Does this meet your needs?

HTH,
Crook
 
R

RandyK

That sort of answers my question... Do you change the booking value for the
resource too?
--
Thanks much!
Randy


Crook said:
Hi Randy,

As admin, what I do is inactivate the resource in PWA on the admin page.
Then Project Pro 2003 alerts each PM who planned work for that resource that
there is work pending for an inactive resource whenever a project containing
that resource is opened. Does this meet your needs?

HTH,
Crook
 
C

Crook

Hi Randy,

As a PM, I usually don't bother changing the booking value from committed to
proposed. As a PM, the main thing I concentrate on is zeroing out any
remaining hours for an inactive resource.

HTH,
Crook

RandyK said:
That sort of answers my question... Do you change the booking value for
the
resource too?
 
Top