Inactive resource being assigned new work

R

Reuben Hecquet

PS 2003 and PP 2003 both with SP1.

We are carrying out the following procedure when a resource should be
set to inactive:

Open PP set remaining work to 0 for this resource.

Member of admin team set resource as inactive

Do not assign any task to this resource in future

We have a problem though that if a task that this resource was
assigned to is rescheduled the inactive resource is assigned new time.

Are we carrying out the right steps or have we made a mistake or
misunderstanding. Any help much appreciated.

Rgds
Reuben
 