Inconsistency in Available Time

J

jvgeest

PWA for MS Project Server 2007 shows an inconsistency between assignments and
available time. In some cases the assignments are not visible in the
availability calculation. In 1 example the assignment overview gives an 8
hour task on Monday and the availability still gives 8 hours on Monday. Every
change has been saved and published. In another example 3 tasks of 5 working
days each result in wrong availability calculations whereas 1 task of 15
working days calculates the right availability. Any suggestions?
 
J

jvgeest

There is no difference in the availability figures for estimated or committed
tasks. Another thing I noticed: the availability is fine in the resource
usage view of the project where the task is defined. In other projects the
availability is wrong in the resource usage view. I only used enterprise
resources.

Thanks,
JvGeest
 
B

Ben Howard

For Project Pro, check the resource availability with teh Load Summary
Resource Assignments button checked.

I would also republish all the projects one by one and then check the data.
If it is still incorrect then it's likely a bug somewhere.
 
J

jvgeest

I've checked it all and no improvements. I've just seen that opening another
project immediately influences the availability. So opening 2 projects at the
same time gives a different (better) result than opening 1 project. When
closing one of the projects the availability is wrong again, just for a
specific date. Other values from the closed project are still fine.

Thanks,
JvGeest
 