I published a project plan this morning with some revised assignment data. I
used publish New and Changed Assignments to do so. However when I look at
the View Resource Assignments View in PWA, the new changes do not appear. I
am looking specifically for resource availability here.
And how does the resource availability information in PWA differ (if at all)
from the information I see when using the Resource Graphs option in Project
Professional ?
Why not ?
And what do I have to do to resolve the issue ?
Thanks
Gary
I published a project plan this morning with some revised assignment data. I
used publish New and Changed Assignments to do so. However when I look at
the View Resource Assignments View in PWA, the new changes do not appear. I
am looking specifically for resource availability here.
And how does the resource availability information in PWA differ (if at all)
from the information I see when using the Resource Graphs option in Project
Professional ?
Why not ?
And what do I have to do to resolve the issue ?
Thanks
Gary